by Bart Kolosowski | Nov 29, 2021
Tender pack for a 4-unit residential project in London The challenge A developer had negotiated with a contractor without the aid of a quantity surveyor, which led to a drastic increase in costs and a very delayed start on a four-unit residential project in London....
by Bart Kolosowski | Nov 23, 2019
Final account settlement of a residential project The challenge A contractor believed they were due £340,000 in variations on the agreed project cost but the contract administrator was only willing to pay an additional £70,000. Our solution We reviewed the account,...
by Bart Kolosowski | Nov 23, 2019
Commercial building conversion into 24 flats The challenge A contractor faced a cash-flow problem 3 months into a project to convert a West London commercial building into 24 flats. Our solution We reviewed the build costs and discovered there was no detailed data...
by Bart Kolosowski | Nov 16, 2019
Fast track delivery of three houses The challenge A contractor had to deliver three new build homes in West London with only a nine month construction period and a two week mobilisation period. Our solution We created an eight month programme to ensure the project...