Tender pack for a 4-unit residential project in London

Tender pack for a 4-unit residential project in London The challenge   A developer had negotiated with a contractor without the aid of a quantity surveyor, which led to a drastic increase in costs and a very delayed start on a four-unit residential project in London....

Final account settlement of a residential project

Final account settlement of a residential project The challenge   A contractor believed they were due £340,000 in variations on the agreed project cost but the contract administrator was only willing to pay an additional £70,000. Our solution  We reviewed the account,...

Commercial building conversion into 24 flats

Commercial building conversion into 24 flats The challenge   A contractor faced a cash-flow problem 3 months into a project to convert a West London commercial building into 24 flats. Our solution  We reviewed the build costs and discovered there was no detailed data...

Fast track delivery of 3 houses

Fast track delivery of three houses The challenge   A contractor had to deliver three new build homes in West London with only a nine month construction period and a two week mobilisation period. Our solution  We created  an eight month programme to ensure the project...

Why employ a construction cost consultant?

You need specialist skills that you may not have in your team. It can also mean a lot of extra time is required, which you may not have available.

Learn More

Thank you